What are the Steps to Installing a Hydraulic Mold Upender?

Share Post :

What are the Steps to Installing a Hydraulic Mold Upender?

Installing heavy industrial machinery like a hydraulic mold upender presents significant challenges. The process demands precision, adherence to safety protocols, and technical know-how. Mistakes during setup can lead to equipment damage, costly downtime, operational inefficiencies, and most critically, severe safety hazards for personnel. Following a structured, manufacturer-approved installation procedure is essential.

Hydraulic equipment setup

Installing a hydraulic mold upender involves several crucial steps: site preparation, careful unloading and inspection, precise positioning and leveling, secure anchoring to the foundation, connecting hydraulic and electrical systems correctly, filling with hydraulic fluid, purging air, performing initial operational tests, and ensuring all safety mechanisms are functional before handover. Strict adherence to safety protocols throughout is paramount for a successful and safe installation.

Understanding these steps in detail ensures that the equipment functions reliably and safely from day one. Let’s break down each phase of the installation process, highlighting key considerations and best practices derived from industry standards and manufacturer guidelines.

Pre-Installation: Planning and Site Preparation

Proper planning is the bedrock of a successful hydraulic mold upender installation, preventing costly errors and ensuring safety. This initial phase involves thorough site assessment, including verifying foundation strength and levelness, checking utility availability, and confirming adequate clearances. Reviewing manufacturer specifications and local regulations beforehand helps anticipate requirements and potential challenges, setting the stage for a smooth and efficient setup process before the equipment arrives.

Pre-installation planning encompasses confirming the foundation meets the upender’s weight and dynamic load requirements, ensuring sufficient space for the machine’s footprint, operational movement, and maintenance access. Key activities include verifying electrical power supply adequacy, reviewing manufacturer’s drawings and installation manuals, and complying with all federal, state, and local codes. Upon receiving the equipment, immediately inspect it against the bill of lading, report any shipping damage or shortages to the carrier and vendor, carefully remove crating materials ensuring no components are discarded, and identify all parts including fasteners, controls, and manuals. The installation site must be clean, level within specified tolerances (e.g., 1/8 inch over 5 feet), and free from obstructions.

installation process

Foundation and Unpacking Requirements

The success of the installation heavily relies on the adequacy of the foundation and the diligence applied during unpacking and initial inspection.

  • Foundation Integrity: The concrete floor or foundation must be designed to support the total weight of the upender plus its maximum rated load capacity. Consult the manufacturer’s specifications for minimum concrete strength (PSI) and thickness. The surface must be level; the Uni-Craft manual specifies a tolerance of 1/8 inch over 5 feet if shimming and grouting are not used. Uneven surfaces necessitate the use of solid shims placed under the base frame, potentially followed by grouting to ensure full, stable support and prevent frame distortion. If the upender is installed in a pit, specific safety measures like bevel toe guards or equivalent protection are mandatory to prevent shear point hazards.
  • Unpacking Procedure: Exercise caution when removing crating. Use the provided checklist (similar to the one mentioned in the Uni-Craft manual) to verify receipt of all items against the bill of lading. Inspect thoroughly for any damage incurred during transit. Look for loose boxes, accessories, manuals, or components like fasteners or guards attached to the crating material. Ensure nothing essential is accidentally discarded.
  • Damage Reporting: If any damage or shortage is discovered, report it immediately to both the carrier and the vendor. Obtain a signed damage report from the carrier. Do not attempt repairs or modifications before filing the report and receiving instructions, as this could void warranty claims or return authorizations. Written return authorization from the factory is typically required before sending any equipment back.
  • Component Identification: Familiarize yourself with all components, including the base frame, platform weldment, hydraulic cylinders, power unit (internal or external), control pendant, safety labels, and any optional features. Ensure all necessary fasteners and hardware are present.

Below is a basic checklist to ensure site readiness before the main installation begins:

Site Preparation Checklist Item Status (Check when Complete) Notes
Foundation Strength Verified Matches manufacturer’s load specs.
Foundation Levelness Checked Within tolerance (e.g., 1/8" per 5 ft) or shims/grout planned.
Required Clearances Confirmed Adequate space for operation, loading/unloading, and maintenance.
Electrical Power Availability Verified Correct voltage, phase, and amperage available near the location.
Installation Area Clean & Clear Free of debris, obstructions, and potential hazards.
Unpacking Complete & All Parts Identified Compared against Bill of Lading; manuals and fasteners located.
Initial Equipment Inspection Done Checked for shipping damage; report filed if necessary.
Local Code Compliance Reviewed Installation plan aligns with relevant safety and building codes.

Completing these pre-installation steps diligently minimizes unforeseen problems during the physical installation and commissioning phases.

Mechanical Installation: Positioning and Anchoring

With the site prepared and the equipment inspected, the next critical phase is the mechanical installation, involving the careful lifting, precise positioning, and secure anchoring of the hydraulic mold upender. This stage demands adherence to safe lifting practices and meticulous attention to alignment and fastening to ensure operational stability and safety.

Mechanical installation focuses on safely lifting the upender, typically using designated lifting brackets or appropriate slings placed around the base frame corners, avoiding damage to structural members or components. The unit must be positioned precisely, maintaining specified clearances (e.g., a 1-inch gap around the platform). Leveling is achieved using solid shims under the base if the floor isn’t perfectly flat. Finally, the upender must be securely anchored using appropriately sized, high-strength anchor bolts installed per manufacturer instructions.

step-by-step guide

Lifting, Leveling, and Securing the Upender

Executing this phase correctly is crucial for the longevity and safe operation of the equipment.

  1. Safe Lifting: Hydraulic upenders are heavy; use lifting equipment (forklift, crane) with adequate capacity. If the unit has designated lifting brackets (as mentioned in the Bushman manual), use those. Otherwise, employ heavy-duty slings positioned around the main base frame structure, ensuring the load is balanced and stable during the lift. Protect hydraulic lines, electrical components, and finished surfaces from sling damage. Only trained personnel should perform lifting operations.
  2. Positioning and Alignment: Carefully lower the upender into its designated location. Ensure it is aligned correctly relative to workflow patterns (e.g., interfacing conveyors or workstations). Crucially, maintain the manufacturer-specified clearances around moving parts, such as the 1-inch clearance around the platform mentioned in the Uni-Craft manual. This prevents binding and potential pinch points.
  3. Leveling: A level base is essential for proper operation and to prevent undue stress on the frame and pivot points. If the foundation is not perfectly level (within the 1/8" per 5 ft tolerance), place solid metal shims under the base frame at anchor points until the unit is perfectly level in both directions. Ensure the shims provide full support. Some installations may require grouting under the base frame after leveling and initial anchoring for maximum stability, especially in high-cycle or heavy-load applications.
  4. Anchoring: Operating an unanchored upender is extremely dangerous. The base frame typically includes anchor clips or lag-down brackets with holes.
    • Use the anchor clip holes as guides to drill holes into the concrete foundation to the correct diameter and depth for the specified anchor bolts (e.g., Grade 8 bolts mentioned in the Bushman manual).
    • Clean the drilled holes thoroughly.
    • Install the anchor bolts (e.g., wedge anchors) through the clips/brackets into the holes. Ensure the bolt fit is close to restrict shifting.
    • Drive the anchor bolts to the correct depth, ensuring sufficient thread engagement below the anchor clip surface (e.g., minimum six to seven threads as per Uni-Craft manual).
    • Tighten the nuts progressively and evenly to the manufacturer’s recommended torque specification. The Uni-Craft manual suggests three or four turns past finger-tight as a starting guide for wedge anchors, but always refer to the specific anchor bolt manufacturer’s torque requirements. Over-tightening can damage the anchor or concrete, while under-tightening compromises stability.
  5. Post-Anchoring Check: After initial tightening, operate the upender through a few cycles (once systems are connected) and then re-check and re-tighten the anchor bolts as necessary, as initial operation can cause minor settling.

Proper positioning and secure anchoring are fundamental safety requirements, preventing movement or tipping during the dynamic forces exerted during the tilting cycle.

System Connections: Hydraulics and Electrical

Incorrect hydraulic or electrical connections are common installation pitfalls that can severely compromise safety and performance. Leaking hydraulic fluid creates slip hazards and can lead to system failure, while improper wiring poses risks of electrical shock, component damage, and fire. Meticulous adherence to connection procedures is vital. Following schematics and torque specifications ensures system integrity.

System connection involves carefully routing hydraulic hoses to avoid pinching or abrasion, connecting them to the correct ports on the power unit and cylinders, and tightening fittings (like JIC or NPT) to specified torque values using appropriate sealants only where required (e.g., Teflon tape on NPT threads, applied correctly). Electrical connection entails wiring the motor according to the nameplate voltage and phase, verifying correct rotation for 3-phase motors, connecting the control pendant/station, and ensuring all safety circuits (limit switches, emergency stops) are wired correctly per the provided schematics.

step-by-step guide

Ensuring Leak-Free Hydraulics and Safe Electrics

Precision during this stage prevents future headaches and hazards.

Hydraulic Connections:

  1. Identify Ports: Correctly identify inlet (suction), outlet (pressure), and return ports on the pump, valves, and cylinders based on manufacturer diagrams. Cross-connecting lines can cause malfunction or damage.

  2. Hose Routing: Route hoses carefully to avoid sharp bends, twisting, abrasion against machine parts, or potential pinch points during upender movement. Use clamps or guides where necessary to secure hoses.

  3. Fitting Types and Tightening: Hydraulic systems use various fitting types:

    • NPT (National Pipe Taper): Relies on thread interference for sealing. Always use an appropriate sealant like PTFE tape or liquid sealant. Caution: Apply tape starting 1-1.5 threads back from the leading edge and use only 2 wraps to prevent tape fragments from contaminating the system. Do not overtighten NPT fittings, especially swivel types, as this can crack the fitting. Tighten just enough to seal.
    • JIC (Joint Industry Council) 37° Flare: Seals via metal-to-metal contact between the flared tube end and the fitting nose. Lubricate threads and flare surface lightly with hydraulic oil. Tighten nut finger-tight, then use wrenches to tighten by a specific number of flats (FFFT – Flats From Finger Tight) or to a specific torque value as per the table below (adapted from Uni-Craft manual). Over-torquing can damage the flare.
    • SAE O-Ring Boss (ORB) / Face Seal (ORFS): Seals using a captive O-ring. Ensure the O-ring is present, correctly seated, and lubricated. Tighten to specified torque; the seal is made by O-ring compression, not excessive torque.
  4. Torque Values: Always use a torque wrench for critical fittings like JIC. Referencing the Uni-Craft manual’s example for JIC fittings:

    Tube Size (Dash Size) F.F.F.T. (Flats From Finger Tight) Torque (lb-ft, min/max, Threads Lubricated)
    -4 2 11 – 12
    -6 1 1/2 18 – 20
    -8 1 1/2 36 – 39
    -10 1 1/2 57 – 63
    -12 1 1/4 79 – 88
    -16 1 108 – 113

    Note: Always consult the specific manufacturer’s manual for exact values for your equipment.

  5. Leak Check: After filling and pressurizing the system, thoroughly inspect all connections for leaks. Tighten slightly if needed, but avoid overtightening.

Electrical Connections:

  1. Code Compliance: All wiring must conform to national (e.g., NEC in the US), state, and local electrical codes. Work must be performed by qualified electricians.
  2. Power Supply: Connect the main power supply to the motor starter or control panel via a lockable disconnect switch. Ensure the voltage, phase, and frequency match the motor nameplate.
  3. Motor Wiring & Rotation: Wire the motor according to the provided schematic (check for specific diagrams for single-phase or three-phase, like those in the Uni-Craft manual, pages 24-25). Crucial for 3-phase motors: Briefly "jog" the motor to check its rotation direction. If it’s incorrect (pump may run backward, causing damage quickly), swap any two of the three power leads (e.g., L1 and L3) at the starter. Caution: Running a hydraulic pump backward for even 30 seconds can cause severe damage. Use very short jogs for testing.
  4. Control Station: Connect the control pendant or operator station wiring according to the schematic. Ensure the station is located where the operator has a clear view of the upender during operation. Clearly label all controls.
  5. Safety Circuits: Wire all safety devices meticulously – limit switches (to stop travel at ends), emergency stop buttons (should act directly on the control circuit and require manual reset), interlocks (if applicable), and any optional devices like electric toe guards. Safety circuits should be designed to be fail-safe (power failure or device failure results in a safe condition).
  6. Grounding: Ensure the upender frame and electrical panel are properly grounded according to code.

Double-checking all connections against schematics before applying power is essential for preventing damage and ensuring safety.

Commissioning: Fluid Fill, Testing, and Safety Checks

The final commissioning phase bridges the gap between physical installation and operational readiness. It involves carefully filling the hydraulic system, purging trapped air, conducting initial operational tests without load, and meticulously verifying all safety features. This systematic approach ensures the hydraulic mold upender operates smoothly, reliably, and safely before being handed over for production use.

technical installation

Commissioning commences by filling the hydraulic reservoir to the indicated level with clean, manufacturer-recommended hydraulic fluid of the correct type and viscosity. Using a filter cart during filling is highly advised to prevent contamination. The system must then be purged of air; this is typically achieved by briefly jogging the motor to prime the pump, then repeatedly cycling the upender through its full range of motion several times. Holding the ‘down’ control for a few extra seconds when fully tilted can help bleed air from cylinders. Initial operational tests involve checking for smooth, jerk-free movement, verifying the responsiveness and correct function of all controls (up, down, stop), confirming that limit switches accurately stop motion at the travel limits, and performing a thorough visual inspection for any hydraulic leaks or abnormal noises. Finally, all safety guards, labels, and devices must be confirmed to be in place and functioning correctly before the equipment is cleared for operation.

Detailed commissioning steps include:

  1. Hydraulic Fluid Selection & Filling: Use only the hydraulic fluid type and viscosity grade recommended by the manufacturer (e.g., ISO VG 32 or 46 Anti-Wear hydraulic oil, see Uni-Craft manual page 21 for examples). Ensure the fluid is new and clean; filtering new oil from drums is recommended as it often contains contaminants. Fill the reservoir to the level indicated on the sight glass or dipstick. Do not overfill. Ensure the reservoir breather cap is clean and functional.
  2. Pump Priming (If Necessary): Some pump configurations (especially if mounted above the fluid level) may require manual priming. This might involve filling the pump casing or suction line with fluid before the first start. Consult the manual (Uni-Craft Appendix 1 mentions filling the pump case drain for external pumps).
  3. Air Purging: Trapped air causes spongy, jerky operation and can damage components through cavitation. After initial fluid fill and confirming correct motor rotation:
    • Jog the motor briefly several times to help the pump prime.
    • Cycle the upender up and down through its full 90-degree range multiple times at low speed/pressure if possible. Listen for unusual noises.
    • As mentioned in the Uni-Craft manual (page 14), actuate the upender halfway several times, then fully tilt, holding the down control for an extra 10 seconds each time when fully tilted (or fully lowered) to help force air out of the cylinders and back to the reservoir.
    • Continue cycling until operation is smooth and consistent.
  4. Initial Operational Tests (No Load):
    • Verify control functions: Check that the ‘UP’ and ‘DOWN’ buttons operate correctly. If using constant pressure ("deadman") controls, ensure motion stops immediately when the button is released. If using maintained controls, check that limit switches stop the motion reliably at the end of travel and that the ‘STOP’ button functions correctly.
    • Check speed and smoothness: Observe the tilting motion for smoothness. Initial jerkiness due to air should dissipate after purging. Persistent jerky or slow operation might indicate issues (see Troubleshooting, Uni-Craft manual page 23).
    • Check limit switches: Ensure the upender stops automatically and precisely at both the fully horizontal and fully vertical positions. Adjust if necessary (see Bushman manual page 13), but do not adjust to allow over-travel.
    • Listen for abnormal noise: Pay attention to noises from the pump, motor, or pivot points. Unusual humming, grinding, or banging requires investigation.
    • Check for leaks: After cycling, meticulously inspect all hydraulic fittings, hoses, cylinder seals, and the power unit for leaks. Clean up any spilled fluid immediately to avoid misinterpreting it as a leak later.
  5. Safety System Verification:
    • Confirm all guards (e.g., chain guards if applicable, guards around pinch points) are securely installed.
    • Verify emergency stop buttons function correctly, stopping all motion instantly and requiring a manual reset.
    • Check any additional safety devices (bellows, toe guards) for proper operation and condition.
    • Ensure all safety labels are present, legible, and correctly located (referencing Uni-Craft manual pages 4-5).
  6. Load Testing (Optional but Recommended): If feasible and safe, perform initial tests with a partial or full rated load (never exceed capacity) to observe performance under operational conditions. Monitor for strain, speed changes, or instability.
  7. Operator Handover: Provide the end-users and maintenance personnel with the operation and maintenance manuals. Instruct users on proper operation, safety precautions, load capacity limits, and daily checks. Ensure maintenance personnel understand the required maintenance schedules and procedures, including lockout/tagout.

Completing these commissioning steps thoroughly ensures the hydraulic mold upender is ready for safe, efficient, and reliable service.

Conclusion

Successfully installing a hydraulic mold upender hinges on meticulous planning, adherence to manufacturer guidelines, and an unwavering commitment to safety throughout the process. From rigorous site preparation and careful mechanical positioning to precise hydraulic and electrical connections and thorough commissioning tests, each step is critical. Proper Hydraulic equipment setup ensures not only the operational efficiency and longevity of the mold upender but also, most importantly, the safety of the personnel who operate and maintain it. Following these structured steps minimizes risks and lays the foundation for reliable performance.

Send us a message

Whenever you need us, we’re here for you.

Looking for supportive from the expert

Send us a message

Don't hesitate to contact us for more information.

Email Support

info@fhopepack.com

Head Office


Shanghai - China

Let's Talk

Phone : (+86) 13951501635

Mon - Sat : 09.00 - 17.00

Exit mobile version