Coil Packing Line Project Timeline & Lead Times | FHOPE
Our coil packing line project stages from quotation and layout to manufacturing, delivery in 90–150 days, installation, commissioning and site acceptance.
Tiến độ dự án dây chuyền đóng gói cuộn thép: Từ thiết kế đến nghiệm thu (SAT)
Tiến độ dự án dây chuyền đóng gói cuộn thép: Từ thiết kế đến nghiệm thu (SAT)
Buyers usually ask two questions about an dây chuyền đóng gói cuộn dây tự động project: how long it takes, and what happens at each stage. Below is how our projects run, with the lead times we quote.
Stage 1: Coil Data and Line Layout
We start with your coil range (weight, OD, ID, width), required output, packaging specification and site layout. With these we prepare the line configuration and a layout drawing.
We size the line by its slowest station. For example, a down-ender can take 20–60 s per coil depending on the model, and strapping takes about 15–20 s per strap.
The image shows an engineering team reviewing a coil packaging line solution. Stage 1 starts with coil data and the site layout, and it ends with a line configuration and a layout drawing.
Stage 2: Quotation and Order
Our quotations list each station, the main component brands, the spare parts and the terms. Typical terms are a 50% down payment by T/T and the 50% balance before delivery.
Stage 3: Engineering and Manufacturing
| Trang Bị | Typical delivery after down payment |
|---|---|
| Coil packing line (down-ender + wrapper + controls) | Khoảng 90 ngày |
| Larger lines with coil cars and eye-through wrapping systems | Khoảng 120 ngày |
| Automatic radial steel coil strapping machine | Khoảng 150 ngày |
These are factory lead times after the down payment; ocean freight and on-site installation are added on top.
The engineering documents we supply include the CAD wiring diagram, terminal diagram, control panel diagram and PLC program (STEP7 for Siemens).
The image shows a heavy-duty steel coil wrapping machine packing line. Manufacturing lead times start from the down payment and differ by line scope.
Stage 4: Factory Acceptance Testing (FAT)
After building, we run and debug the machine in our factory, and you inspect it there.
Alternatively, you can accept the machine remotely: we test-run it and send inspection videos and photos.
Stage 5: Shipment
Machines ship in standard export packing, or by FCL container on larger projects.
Switch cabinets are about 800 mm wide on small machines and 1200–1600 mm on medium machines; on large lines the cabinet system ships in units no wider than 3600 mm.
Stage 6: Installation and Commissioning
Our engineers handle installation and commissioning on site. Meanwhile, the customer prepares the foundations, power and compressed air (see our site preparation guide).
The image shows a steel coil packing line installed in a plant. Our engineers handle installation and commissioning on site.
Stage 7: Site Acceptance (SAT) and Handover
After installation and commissioning, you run the machine on site for the site acceptance test. Typical on-site durations are 1–2 days for small machines, about 1 week for customized machines, 10–15 days for large customized machines, and about 30 days for a large complete project.
Operator training takes 1–3 days (3 days on automatic lines). After handover the 2-year warranty starts, and we provide lifetime technical support.
Watch an automatic copper coil packaging line with two-stage wrapping and stacking:
FAQ
Bao lâu một dây chuyền đóng gói cuộn dây lấy? About 90 days after the down payment for a standard line (down-ender, wrapper and controls). Larger lines take 120 days, and radial strapping machines 150 days, plus shipping and on-site installation (from 1–2 days for small machines to about 30 days for a large complete project).
What documents do I receive? CAD wiring, terminal and control panel diagrams, the PLC program (STEP7 for Siemens), and a spare parts list.
Who installs the line? Our engineers install and commission it on site.
What warranty starts at handover? A 2-year warranty, plus lifetime technical support.
Chi tiết hình ảnh
Nhấn vào đây để phóng to
Nhấn vào đây để phóng to
Nhấn vào đây để phóng to
Nhấn vào đây để phóng to
Xem cách nó hoạt động
Khám phá cách các giải pháp đóng gói tự động của chúng tôi tối ưu hóa hiệu quả dây chuyền sản xuất của bạn. Video này minh họa hoạt động liền mạch được thiết kế để bảo vệ sản phẩm tối đa.
Được tin cậy bởi Các nhà máy thép và các nhà lãnh đạo ngành công nghiệp
Các nhà sản xuất toàn cầu tin dùng thiết bị đóng gói hạng nặng của FHOPE.
Bạn đã sẵn sàng tối ưu hóa dây chuyền đóng gói của mình chưa?
Nhận báo giá tùy chỉnh kèm phân tích lợi tức đầu tư (ROI). Kỹ sư của chúng tôi sẽ phản hồi trong vòng 24 giờ.
- Thiết kế bố cục miễn phí
- Hỗ trợ lắp đặt toàn cầu
- Bao gồm bảo hành 2 năm
Thông tin của bạn được bảo mật và sẽ không bao giờ được chia sẻ.