Our coil packing line project stages from quotation and layout to manufacturing, delivery in 90–150 days, installation, commissioning and site acceptance.

Chứng nhận CE
ISO 9001
2 năm bảo hành
Tiến độ dự án dây chuyền đóng gói cuộn thép: Từ thiết kế đến nghiệm thu (SAT)

Tiến độ dự án dây chuyền đóng gói cuộn thép: Từ thiết kế đến nghiệm thu (SAT)

Tiến độ dự án dây chuyền đóng gói cuộn thép: Từ thiết kế đến nghiệm thu (SAT)

Buyers usually ask two questions about an dây chuyền đóng gói cuộn dây tự động project: how long it takes, and what happens at each stage. Below is how our projects run, with the lead times we quote.

Stage 1: Coil Data and Line Layout

We start with your coil range (weight, OD, ID, width), required output, packaging specification and site layout. With these we prepare the line configuration and a layout drawing.

We size the line by its slowest station. For example, a down-ender can take 20–60 s per coil depending on the model, and strapping takes about 15–20 s per strap.

Stage 1 starts with coil data — weight, OD, ID, width — and the required output, not with a calendar date.

The image shows an engineering team reviewing a coil packaging line solution. Stage 1 starts with coil data and the site layout, and it ends with a line configuration and a layout drawing.

Stage 2: Quotation and Order

Our quotations list each station, the main component brands, the spare parts and the terms. Typical terms are a 50% down payment by T/T and the 50% balance before delivery.

Stage 3: Engineering and Manufacturing

Trang Bị Typical delivery after down payment
Coil packing line (down-ender + wrapper + controls) Khoảng 90 ngày
Larger lines with coil cars and eye-through wrapping systems Khoảng 120 ngày
Automatic radial steel coil strapping machine Khoảng 150 ngày

These are factory lead times after the down payment; ocean freight and on-site installation are added on top.

The engineering documents we supply include the CAD wiring diagram, terminal diagram, control panel diagram and PLC program (STEP7 for Siemens).

Manufacturing lead times start from the down payment and differ by line scope: 90 days for a standard line, up to 150 days for a radial strapping machine.

The image shows a heavy-duty steel coil wrapping machine packing line. Manufacturing lead times start from the down payment and differ by line scope.

Stage 4: Factory Acceptance Testing (FAT)

After building, we run and debug the machine in our factory, and you inspect it there.

Alternatively, you can accept the machine remotely: we test-run it and send inspection videos and photos.

Stage 5: Shipment

Machines ship in standard export packing, or by FCL container on larger projects.

Switch cabinets are about 800 mm wide on small machines and 1200–1600 mm on medium machines; on large lines the cabinet system ships in units no wider than 3600 mm.

Stage 6: Installation and Commissioning

Our engineers handle installation and commissioning on site. Meanwhile, the customer prepares the foundations, power and compressed air (see our site preparation guide).

Installation and commissioning are handled by our engineers on site, with foundations, power and compressed air prepared by the customer.

The image shows a steel coil packing line installed in a plant. Our engineers handle installation and commissioning on site.

Stage 7: Site Acceptance (SAT) and Handover

After installation and commissioning, you run the machine on site for the site acceptance test. Typical on-site durations are 1–2 days for small machines, about 1 week for customized machines, 10–15 days for large customized machines, and about 30 days for a large complete project.

Operator training takes 1–3 days (3 days on automatic lines). After handover the 2-year warranty starts, and we provide lifetime technical support.

Watch an automatic copper coil packaging line with two-stage wrapping and stacking:

FAQ

Bao lâu một dây chuyền đóng gói cuộn dây lấy? About 90 days after the down payment for a standard line (down-ender, wrapper and controls). Larger lines take 120 days, and radial strapping machines 150 days, plus shipping and on-site installation (from 1–2 days for small machines to about 30 days for a large complete project).

What documents do I receive? CAD wiring, terminal and control panel diagrams, the PLC program (STEP7 for Siemens), and a spare parts list.

Who installs the line? Our engineers install and commission it on site.

What warranty starts at handover? A 2-year warranty, plus lifetime technical support.

Chi tiết hình ảnh

Coil Packing Line Project Timeline: From Design to SAT - Detail 1

Nhấn vào đây để phóng to

Coil Packing Line Project Timeline: From Design to SAT - Detail 2

Nhấn vào đây để phóng to

Coil Packing Line Project Timeline: From Design to SAT - Detail 3

Nhấn vào đây để phóng to

Coil Packing Line Project Timeline: From Design to SAT - Detail 4

Nhấn vào đây để phóng to


Xem nó trong hành động

Xem cách nó hoạt động

Khám phá cách các giải pháp đóng gói tự động của chúng tôi tối ưu hóa hiệu quả dây chuyền sản xuất của bạn. Video này minh họa hoạt động liền mạch được thiết kế để bảo vệ sản phẩm tối đa.

Thông lượng cao
Lên đến 60 cuộn dây mỗi giờ
Chất lượng phù hợp
Mỗi lớp bọc đều đáp ứng tiêu chuẩn kỹ thuật.
Báo giá

Được tin cậy bởi Các nhà máy thép và các nhà lãnh đạo ngành công nghiệp

Các nhà sản xuất toàn cầu tin dùng thiết bị đóng gói hạng nặng của FHOPE.

ArcelorMittal POSCO Thép nippon Nucor Thép Tata ArcelorMittal POSCO Thép nippon Nucor Thép Tata

Bạn đã sẵn sàng tối ưu hóa dây chuyền đóng gói của mình chưa?

Nhận báo giá tùy chỉnh kèm phân tích lợi tức đầu tư (ROI). Kỹ sư của chúng tôi sẽ phản hồi trong vòng 24 giờ.

  • Thiết kế bố cục miễn phí
  • Hỗ trợ lắp đặt toàn cầu
  • Bao gồm bảo hành 2 năm

Thông tin của bạn được bảo mật và sẽ không bao giờ được chia sẻ.

Máy liên quan

Dây chuyền đóng gói thép cuộn

Dây chuyền đóng gói thép cuộn

Xem chi tiết →
Dây chuyền đóng gói cuộn dây dọc

Dây chuyền đóng gói cuộn dây dọc

Xem chi tiết →
Dây chuyền đóng gói cuộn dây

Dây chuyền đóng gói cuộn dây

Xem chi tiết →
Dây chuyền đóng gói cuộn dây đồng

Dây chuyền đóng gói cuộn dây đồng

Xem chi tiết →
Dây chuyền đóng gói cuộn dây

Dây chuyền đóng gói cuộn dây

Xem chi tiết →
Dây chuyền đóng gói bảng điều khiển

Dây chuyền đóng gói bảng điều khiển

Xem chi tiết →
Máy đóng bao ống

Máy đóng bao ống

Xem chi tiết →
Dây chuyền đóng gói hồ sơ nhôm

Dây chuyền đóng gói hồ sơ nhôm

Xem chi tiết →
FHOPE Dây chuyền bó & đóng đai ống tự động

FHOPE Dây chuyền bó & đóng đai ống tự động

Xem chi tiết →
Dây chuyền đóng đai và bó ống tự động

Dây chuyền đóng đai và bó ống tự động

Xem chi tiết →
Máy đóng đai ống thép tự động

Máy đóng đai ống thép tự động

Xem chi tiết →
Máy đóng gói ống thép tự động FHOPE

Máy đóng gói ống thép tự động FHOPE

Xem chi tiết →
Dây chuyền đóng gói ống nhựa tự động

Dây chuyền đóng gói ống nhựa tự động

Xem chi tiết →
Dây chuyền đóng bao ống PPR / PVC tự động

Dây chuyền đóng bao ống PPR / PVC tự động

Xem chi tiết →
Máy đóng gói túi ống platsic

Máy đóng gói túi ống platsic

Xem chi tiết →
Máy đóng gói săm lốp FPT-200

Máy đóng gói săm lốp FPT-200

Xem chi tiết →
Máy đóng gói săm lốp FPT-300

Máy đóng gói săm lốp FPT-300

Xem chi tiết →
Máy đóng gói săm lốp FPT-400

Máy đóng gói săm lốp FPT-400

Xem chi tiết →
Máy đóng gói cuộn dây cáp-FPCA100

Máy đóng gói cuộn dây cáp-FPCA100

Xem chi tiết →
Máy quấn cuộn cáp FPCA 200

Máy quấn cuộn cáp FPCA 200

Xem chi tiết →