Many plants do not need a new خط بسته بندی کویل اتوماتیک. Their coil cars, skids and up-enders still work, and the problem sits at one or two manual stations. In a retrofit, we connect new automatic machines to the equipment the plant already has, so that the line keeps running while we fix the bottleneck.
Step 1: Measure the Manual Station You Want to Replace
Start with numbers from the existing line. One tender specification we answered described a manual process of paper wrapping, edge protectors and strapping that took 120 seconds per coil and needed four people: one for the coil car and wrapper, and three for manual jobs. Figures like these show where automation pays off and give a clear target for the new equipment.
The image shows a stainless steel coil packing machine line. Measured numbers from the existing line — like the 120 seconds per coil and four people in the manual example — show where automation pays off.
Step 2: Audit Equipment to Keep, Extend or Replace
In that eye-through wrapping retrofit:
- Kept: the existing V-type skids, coil car, up-ender and manual packaging station (now used for other packaging work)
- تمدید شده: the existing coil-car pit, so it could reach a new wrapping position
- اضافه: an eye-through wrapper with an outer edge-protector device and cradle roll station, a new pit-type V-saddle coil car, a hydraulic station and safety fencing
- Interlocked: the old and new coil cars, with automatic and manual safeguards against collision
The image shows an automatic steel coil strapping and stacking conveyor line. In a retrofit, existing equipment is audited one by one: what is kept, what is extended, and what new stations are added around it.
Step 3: Pick the Modules to Add
Our modules can be added one at a time:
| ماژول ها | What it brings to an existing line |
|---|---|
| کویل پایین آورنده | Picks single coils from the turnstile and tilts them 90°; slit coils from 15 mm wide; 20–30 s per coil |
| بستهبندی شفاف | Stretch film (or paper) wrap; overlap 20–90%; PU-covered table rollers |
| Outer edge-protector device (optional) | Applies outer edge protectors automatically during wrapping |
| تسمه کشی PET از طریق چشم | 3, 4 or 6 straps, about 15 s per cycle |
| وزن کردن و برچسب زدن | Weighs, prints and appliies bar-code labels after wrapping |
| Stacker / turntable | Stacks packed coils onto pallets |
Step 4: Align Mechanical, Electrical and Utility Interfaces
Before ordering equipment, agree on these interfaces with the plant:
- مکانیکی: coil-car pits, foundations, skid heights, and the conveyor length at handover points
- برق: we supply the switch cabinets, field wiring and Siemens PLC, plus CAD wiring diagrams and the PLC program. We can also take coil data manually or over Profinet, or share packing data with ERP/MES systems.
- خدمات رفاهی: 380 V/50 Hz is our standard (400 V/60 Hz on request); compressed air at 0.6–0.8 MPa, clean and dry
The image shows an automated coil packing line inside a plant. The retrofit interfaces are agreed around the equipment that already exists: coil-car pits, foundations, skid heights, conveyor lengths, cabinets and utilities.
Step 5: Plan the Cutover and Handover
The existing line should keep producing until the new stations are ready. Agree which station is switched over first and how the old manual station stays available as a fallback. On an automatic line, the changeover time is the installation time: typically 6–10 days, including installation, commissioning, site wiring and integrating our program with the existing site systems. Retrofit equipment carries the same 2-year warranty as our new lines.
Watch an automatic slit coil packing line:
The image shows a coil packing line manufacturing factory. Retrofit modules are built and tested before cutover, and carry the same 2-year warranty as our new lines.
سوالات متداول
Can you add one machine instead of a whole line? Yes. Each module can be integrated into an existing line.
Can the new equipment work with my existing coil car? Yes, it can be interlocked with existing cars. In one retrofit we added a second coil car with anti-collision safeguards.
Do you supply the controls? Yes: PLC, HMI, switch cabinets and field wiring, plus CAD wiring diagrams and the PLC program.
How long is the line down during a retrofit? It depends on the project. On an automatic line, it is typically 6–10 days, including installation, commissioning, site wiring and program integration.
What warranty applies to retrofit equipment? ضمانت 2 ساله.
Send us your current line layout and the station that limits output on your خط بسته بندی کویل اتوماتیک، یا تماس با ما.
جزئیات بصری
اینجا را کلیک کنید تا تصویر را بزرگ تر ببینید.
اینجا را کلیک کنید تا تصویر را بزرگ تر ببینید.
اینجا را کلیک کنید تا تصویر را بزرگ تر ببینید.
اینجا را کلیک کنید تا تصویر را بزرگ تر ببینید.
نحوه کار را تماشا کنید
کشف کنید که چگونه راهکارهای بستهبندی خودکار ما، کارایی خط تولید شما را بهینه میکنند. این ویدیو، عملیات یکپارچهای را که برای حداکثر محافظت طراحی شده است، نشان میدهد.
اعتماد توسط کارخانههای فولاد و رهبران صنعت
تولیدکنندگان جهانی به تجهیزات بستهبندی سنگین FHOPE متکی هستند
آمادهاید تا خط بستهبندی خود را بهینه کنید؟
با تحلیل بازگشت سرمایه، یک پیشفاکتور سفارشی دریافت کنید. مهندسان ما ظرف ۲۴ ساعت پاسخ میدهند.
- طراحی چیدمان رایگان
- پشتیبانی نصب جهانی
- شامل گارانتی 2 ساله
اطلاعات شما امن است و هرگز به اشتراک گذاشته نخواهد شد.